Prime Minister Shehbaz Sharif has taken notice of repeated procurement delays involving nearly Rs. 928 million worth of sports equipment and infrastructure projects ahead of the 2027 South Asian Games, scheduled to take place in Islamabad from April 3 to 11.

Sources told ProPakistani that the Pakistan Sports Board (PSB) has struggled to award contracts for sound amplification systems, electronic timing devices and three diesel generator sets despite several procurement attempts.

Why the Procurement Delays Matter for the 2027 South Asian Games

The South Asian Games are a multi-sport event that brings together athletes from eight nations. Hosting the Games requires a functional venue infrastructure, reliable power supply, and precise timing and scoring equipment. Any shortfall in these areas can affect the credibility of the competition, the safety of participants, and the experience of spectators.

With the Games slated for early April 2027, the window for installing, testing and certifying the equipment is narrowing. The delays have therefore triggered a high-level response, including the Prime Minister's personal notice.

Chronology of the Procurement Attempts

PSB's first effort began in March 2025 when it launched an open competitive bidding process for all three categories of equipment. The only contract awarded at that time was for electronic scoreboards, valued at Rs. 591.334 million, to a joint venture. All other bids were cancelled because the number of qualified respondents was insufficient.

In July 2026 the board switched to a government-to-government (G2G) mechanism, hoping that bilateral agreements would attract foreign suppliers. Only one company submitted a bid, and the Pakistan Engineering Council later confirmed that the firm was not independently registered or licensed as a contractor. The board cancelled the exercise.

Rs. 927.7 Million Procurement Deal Cancelled

September 2026 saw a fresh open bidding advertisement. However, on October 17, just two days before the scheduled bid-submission deadline, the board cancelled the process without opening the technical and financial bids on the Electronic Public Procurement and Disposal System (EPADS). The cancellation left the three projects, electronic timing devices, sound systems and diesel generators, still unfunded.

PSB then invited two additional firms to a direct-contracting exercise. On October 27 it issued a Letter of Intent to one company for the three projects at a combined cost of Rs. 927.758 million. The breakdown was Rs. 309.695 million for electronic timing devices, Rs. 365.193 million for sound systems and Rs. 252.869 million for three diesel generator sets.

Within the first week of November the Letter of Intent was withdrawn after intervention by higher authorities, including the Prime Minister's office. The cancellation re-opened the procurement cycle and added another layer of uncertainty.

Current Status and PSB's Response

When approached for comment, PSB Director General Yawar Hussain said the board had made six attempts to award the projects through government-to-government arrangements. He added that the board now has approval from the Principal Accounting Officer and has re-initiated an open competitive bidding process.

Hussain emphasized that the board is following the guidelines of the Public Procurement Regulatory Authority (PPRA) and that all future bids will be posted on EPADS, where they can be accessed by any qualified bidder.

Implications for Stakeholders

For athletes, delayed equipment means potential disruptions in training schedules and uncertainty about the reliability of timing and scoring systems during competition. For event organisers, the lack of functional diesel generators raises the risk of power outages, especially in indoor arenas that depend on uninterrupted electricity.

Vendors and contractors are also affected. The repeated cancellations have eroded confidence in the procurement process, making it harder for reputable firms to justify the cost of preparing bid documents for a market that appears unstable.

Finally, the Pakistani public, which will host thousands of domestic and foreign visitors, may experience reduced economic benefits if the Games are perceived as poorly organised.

Legal and Institutional Framework Governing the Procurement

The PPRA sets out the rules for open competitive bidding, government-to-government procurement and direct contracting. Under the PPRA, a procurement exercise must attract at least three qualified bidders for open competition; otherwise, the process must be cancelled and re-advertised.

Government-to-government arrangements require that the foreign supplier be a recognized entity and that the contract comply with both Pakistani law and the supplier's domestic regulations. The Pakistan Engineering Council (PEC) is responsible for verifying the licensing status of engineering contractors, a step that halted the July 2026 G2G attempt.

What Comes Next: Timeline and Next Steps

The PSB says the new open bidding round will close by the end of December 2026. Assuming a successful award, the contracts would need to be signed by January 2027 to allow for delivery, installation and testing before the Games begin on April 3, 2027.

If the board again fails to secure sufficient competition, the PPRA mandates a re-advertisement, which could push the timeline into March 2027, leaving only weeks for installation and certification.

Stakeholders are advised to monitor the EPADS portal for upcoming tender notices, and to prepare all required technical and financial documentation well in advance.

Practical Takeaways for Interested Bidders

  • Register on EPADS and ensure your company profile is up-to-date, including all licensing information required by the PEC.
  • Review the detailed technical specifications released by PSB for timing devices, sound systems and generators to avoid disqualification on technical grounds.
  • Prepare financial statements that meet the PPRA's thresholds for eligibility, as financial capacity has been a recurring issue in past attempts.
  • Engage early with the Principal Accounting Officer's office to confirm that any bid meets the fiscal approval requirements.

Broader Context: Pakistan's Sports Infrastructure Development

Pakistan has invested heavily in sports infrastructure over the past decade, with projects ranging from stadium renovations to the construction of new training facilities. The 2027 South Asian Games represent the most high-profile event the country will host in the next ten years, and the government has earmarked significant budgetary allocations for venue upgrades.

However, procurement inefficiencies have plagued several other projects, including the refurbishment of the Jinnah Sports Complex and the installation of flood-lighting at regional stadiums. Analysts note that the pattern of repeated cancellations reflects systemic challenges in aligning technical requirements with the pool of qualified local and foreign suppliers.

Addressing these challenges is essential not only for the Games but also for the long-term development of sports in Pakistan, as modern equipment is a prerequisite for athlete development and international competition readiness.