Capital Development Authority Accelerates Infrastructure Work
The Capital Development Authority has sped up construction on the Margalla Avenue extension from N-5 to M-1 and the Sangjani Interchange. Transport infrastructure in the region receives continuous attention as municipal planners seek to alleviate persistent traffic congestion. City authorities focus heavily on major arterial routes to streamline daily commutes and ease vehicular flow across critical entry points into the capital.
The authority said crews are working around the clock across several sections on the CDA chairman's orders, with 43 percent of the overall project complete. Continuous site inspections and expanded shift schedules ensure that workers maintain rapid progress on multiple fronts. Engineering teams deploy heavy machinery day and night to keep the ambitious civil works on schedule.
Margalla Avenue Extension Progress
Work continues on the roughly 2.7-kilometer extension of the main roadway within Islamabad Capital Territory. This specific stretch of highway forms a vital link for motorists navigating the western boundaries of the municipal limits. Surveyors and builders coordinate closely to align the new asphalt layers with existing road networks, ensuring a smooth transition for high-speed traffic.
All loops and ramps are in the final stages of construction, and crews are also building the service road that connects to the main roadway. These access ramps facilitate seamless merging for vehicles transitioning between regional motorways and local urban streets. The parallel service roads accommodate local traffic, separating neighborhood vehicles from fast-moving transit vehicles.
Underpass and Sangjani Interchange Development
Crews have finished the underpass structure, including its concrete walls and footing slabs. Structural engineers supervised the pouring of high-strength concrete to guarantee long-term durability against heavy truck loads. This underpass eliminates surface-level conflict points, allowing cross-traffic to bypass major bottlenecks safely.
At the Sangjani Interchange, they have completed piling and girder work. Steel reinforcement work is underway, and the CDA expects excavation to finish soon. Rigorous quality control checks accompany every phase of the interchange assembly to meet national civil engineering standards.
N-5 Bridge and Airport Access Construction
At the N-5 bridge, crews have completed piling and excavation for the abutments on both sides. Deep foundation work ensures the bridge piers remain stable across shifting soil conditions near the riverbed. Workers also finished four culverts and are still building the fifth to manage local drainage effectively.
CDA Chairman Sohail Ashraf directed project teams to meet the construction deadline without compromising quality. Senior supervisors hold daily briefing sessions to address supply chain delays and resolve technical bottlenecks swiftly. Maintaining structural integrity remains a top priority alongside hitting milestone dates.
Regional Connectivity and Traffic Impact
Ashraf said the project would provide an important route into Islamabad for people traveling from other cities, particularly those coming from Khyber Pakhtunkhwa. Commuters from neighboring provinces frequently encounter severe delays at older toll plazas and narrow intersections during peak hours. The new multi-lane corridor absorbs heavy transport trucks and passenger cars, significantly cutting down travel times.
He added that it would improve access to Islamabad International Airport for commuters traveling within and outside the capital. Travelers heading toward flight terminals benefit from dedicated bypasses that avoid congested city center streets. Local businesses and transport operators anticipate lower fuel costs and reduced wear on commercial fleets once the entire network opens.